Integral floor formed in one operation, poured and finished simultaneously to control flatness

Concrete pavement sectional pouring, mechanical troweling with one-time finishing

Sky pump, ground pump and mixer truck coordinated feeding, ensuring continuous concrete pouring without interruption

Mechanical power trowel operations with point-by-point flatness verification and acceptance

Slope support and embankment hardening are carried out simultaneously, with concrete pump trucks directly supplying material into the formwork.

Concrete pouring for mountain road sections emphasizes the use of segmented flow construction in narrow sections to improve organizational efficiency and reduce mutual interference between traffic and operations. During construction, formwork installation and finishing processes are required to be synchronized to ensure smooth segment connections, stable surface forming quality, and reduce risks of rework and schedule fluctuations.